WATER AND SANITATION SECTOR PORTFOLIO |
US$ | EC$ | CDB/BNTF PROGRAM | DATE OF AWARD |
PLANNED START |
ACTUAL START |
PLANNED FINISHED |
George Charles Boulevard Public Facility, Castries |
250,650 | 675,477 | 7 | 27 Nov. 2015 | 11 Dec. 2015 | 4 Jan. 2016 | 27 May 2016 |
Ravine Poisson Public Facility Replacement, Bexon, Castries |
184,309 | 496,694 | 7 | 27 Nov. 2015 | 11 Dec. 2015 | 4 Jan. 2016 | 6 May 2016 |
Bouton, Soufriere Water Extension |
600,000 | 1,616,940 | 7 | 28 Oct. 2015 | 16 Nov. 2015 | 23 May 2016 | 28 Aug. 2016 |
Perou Water Supply Upgrade, La Croix Maingot, Castries | 114,440 | 308,404 | 7 | 10 Oct. 2015 | 26 Oct. 2015 | 4 April, 2016 | 10 May, 2016 |